Albondon (600 PE) : the first "French system" in Spain, designed and build in 2005 by AKUT and SINT treats the waste water of a town in the foothills of the Sierra Nevada
Location: Hanningfield, UK
Established: 2012
Project period: 2010-2012
Number of basins: 16
Sludge type: Water works sludge
Sludge production: 1,275 tonnes DS/year
PE, amount: 1.5 - 2.0 million
Construction costs: approxiamtely 6 million £
Wastewater treatment plant for 1200 p.e. at St-Affrique-les-Montagne, south west of France (Tarn), with 1 vertical flow reed bed combined with a surface flow polishing treatment
Two constructed wetlands at Warsco Genk treat the run-off from 1 ha pavement and the cleaning water from a washing street for temporary units.
Client: Greve Municipality
Location: Mosede, Denmark
Established: 1999
Number of basins: 10
Sludge type: Activated sludge
Sludge volume: 1,000 tonnes DS/year
PE, amount: 60,000
Grenoble – urban park Ouagadougou: a 1 ha urban park with reed bed filters and surface flow wetlands collecting and treating stormwater runoff from the roofs of buildings and from adjacent roads in order to meet irrigation needs of the park and to reduce discharge of stormwater into the municipal sewer system. This project was the laureate of the NOVATECH 2013 international conference of sustainable urban drainage award http://novatech.graie.org/a_present_laureats.php